2.12Installation Checklist

-All packing materials and restraints have been removed from each cabinet.

-Each cabinet in the Parallel Capacity/Redundant system is placed in its installed location.

-A ground bond is installed between any cabinets that are bolted together.

-All switchboards, conduits, and cables are properly routed to the SSBM, UPMs and auxiliary cabinets.

-All power cables are properly terminated.

-A ground conductor is properly installed.

-If neutral connection is used, no other N---G bonds exist downstream from the UPMs.

-Battery cables and harness are terminated on E4 and E5.

-Internal battery cabinet connections have been completed (bus bars, plugs, etc.).

-Shunt trip signal wiring is connected from UPMs to battery breaker(s).

-Air conditioning equipment is installed and operating correctly.

-The area around the installed Parallel Capacity/Redundant system is clean and dust-free. (It is recommended that the Parallel Capacity/Redundant system be installed on a sealed concrete pad or a sealed concrete floor.)

-Adequate work space exists around the SSBM, UPMs and other cabinets.

-Adequate lighting is provided around the Parallel Capacity/Redundant system.

-A 120VAC service outlet is located within 25 feet of the Parallel Capacity/Redundant system.

-All circuit breaker trip units settings have been completed per the user’s coordination study.

-Each Remote Monitor Panel (RMP) is mounted in its installed location. (OPTIONAL)

-The control wiring for each RMP is terminated inside the UPS cabinet. (OPTIONAL)

-The Remote Emergency Power Off (EPO) device is mounted in its installed location and its wiring terminated inside the SSBM. (OPTIONAL)

-Summary alarms and/or building alarms are wired appropriately. (OPTIONAL)

-A Relay Interface Module (RIM) is mounted in its installed location and its wiring is terminated inside the SSBM. (OPTIONAL)

-A remote battery disconnect control is mounted in its installed location and its wiring is terminated inside the UPS and battery cabinet. (OPTIONAL)

-Startup and operational checks performed by authorized service personnel.

 

 

 