UNIT START-UP CHECKLIST

MODEL NO.: _________________________________

SERIAL NO.: ______________________________________

SOFTWARE VERSION _________________________

TECHNICIAN: ____________________________________

DATE: _______________________________________

 

PRE-START-UP:

VERIFY THAT DIP SWITCH SETTINGS ARE CORRECT

VERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT

REMOVE ALL COMPRESSOR SHIPPING HOLDDOWN BOLTS AND BRACKETS PER INSTRUCTIONS

VERIFY INSTALLATION OF ECONOMIZER HOOD

VERIFY INSTALLATION OF ALL OPTIONS AND ACCESSORIES

VERIFY THAT ALL ELECTRICAL CONNECTIONS AND TERMINALS ARE TIGHT

CHECK GAS PIPING FOR LEAKS (48A ONLY)

CHECK THAT RETURN-AIR FILTER AND OUTDOOR-AIR FILTERS ARE CLEAN AND IN PLACE

VERIFY THAT UNIT IS LEVEL WITHIN TOLERANCES FOR PROPER CONDENSATE DRAINAGE

CHECK FAN WHEELS AND PROPELLERS FOR LOCATION IN HOUSING/ORIFICE, AND SETSCREW IS TIGHT

VERIFY THAT FAN SHEAVES ARE ALIGNED AND BELTS ARE PROPERLY TENSIONED

VERIFY THAT SUCTION, DISCHARGE, AND LIQUID SERVICE VALVES ON EACH CIRCUIT ARE OPEN

VERIFY THAT CRANKCASE HEATERS HAVE BEEN ON 24 HOURS BEFORE START-UP

START-UP:

ELECTRICAL

SUPPLY VOLTAGE

L1-L2

__________ L2-L3 __________ L3-L1 __________

 

COMPRESSOR AMPS — COMPRESSOR NO. 1

L1

__________

L2

__________

L3 _________

COMPRESSOR AMPS — COMPRESSOR NO. 2

L1

__________

L2

__________

L3 _________

SUPPLY FANS AMPS

(CV)

________

 

EXHAUST FAN AMPS

__________

 

 

(VAV)

________ *

 

 

 

 

 

*VAV fan supply amps reading must be taken with a true RMS meter for accurate readings.

 

TEMPERATURES

 

 

 

 

 

 

 

OUTDOOR-AIR TEMPERATURE

__________ F DB (Dry Bulb)

 

 

 

RETURN-AIR TEMPERATURE

__________ F DB __________

F WB (Wet Bulb)

 

COOLING SUPPLY AIR

 

__________ F

 

 

 

 

GAS HEAT SUPPLY AIR

 

__________ F (48A ONLY)

 

 

 

ELECTRIC HEAT SUPPLY AIR

__________ F (50A ONLY, IF EQUIPPED)

 

 

PRESSURES

 

 

 

 

 

 

 

GAS INLET PRESSURE

 

__________

IN. WG (48A ONLY)

 

 

 

GAS MANIFOLD PRESSURE

STAGE NO. 1 __________ IN. WG

STAGE NO. 2 __________IN. WG (48A ONLY)

REFRIGERANT SUCTION

CIRCUIT NO. 1 __________ PSIG

CIRCUIT NO. 2__________ PSIG

REFRIGERANT DISCHARGE

CIRCUIT NO. 2 __________ PSIG

CIRCUIT NO. 2__________ PSIG

VERIFY REFRIGERANT CHARGE.

Copyright 2010 Carrier Corporation

Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.

Catalog No. 04-53480077-01

Printed in U.S.A.

Form 48/50A-9T

Pg CL-6

6-10

Replaces: 48/50A-7T

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - CUT ALONG DOTTED LINECUT ALONG DOTTED LINE

Page 190
Image 190
Carrier 48/50AJ specifications Unit START-UP Checklist, Pre-Start-Up