Testing and back up

zVerify that all existing portables are working.

zVerify that all existing base stations are working.

Now is the time to add any connections to LTU/SLU/CLU/DTU boards or to move any boards that you have decided to move. Which you do first depends on what you are doing and it is up to you to decide the order of these operations.

zAdd or move any boards.

zAdd or move any cables and 66 blocks.

zLabel or re-label the 66 blocks.

zWhen you are done adding or moving things, DO a system back up. Give it a new name.

zPut the card retention bar on the cabinet.

zPut the bottom plate back on the cabinet.

zPlace the front cover on the cabinet and secure it.