Technical Product Manual - DCT1900

Installation Instructions, Base Station – KRC 101 1371

Caution: Mounting Arms of 12" and 18" are provided. The "creative" use of longer mounting arms is NOT ALLOWED as considerable forces could be generated due to combinations of housing weight, length of the mounting arm, wind loading, earthquakes and/or vibration. These forces could result in pulling out the mounting anchors from the building with destructive results including falling hardware, including possible injury or death to people below.

6.Complete the Installation of the Base Station

After securing the weatherproof housing to the building surface (above), terminate the signal/ power cable inside the housing with the recommended Modular Plug(s), leaving a service-loop of approximately 12". Connect the Modular Plug(s) to the DCT1900 Base Station and install it in the housing by hanging it on the bracket already mounted inside the housing from earlier steps.

After verification of operation, secure the hinged door of the weatherproof housing.

Locate Base Station Mounting Bracket where shown and drill .156 dia. mounting holes.

4.0"

Weatherproof Housing

(rear view)

2 1/4"

Mounting

Bracket (shipped with Base Station)

5.0"

 

6-32 x 5/8"

6-32

pan head

Locking

screw

hex-nut

 

#6

 

flatwasher

 

Fig. 16-13 Base Station Mounting Bracket Attachment to Housing

Install-DCT1900/R8/mw

16-15

© 2000-2005

 

Page 237
Image 237
Nortel Networks DCT1900 manual Weatherproof Housing Rear view