Technical Product Manual - DCT1900

Commissioning, Radio Coverage Verification

3.Move closer to each Base Station and check that the Portable Telephone locks to it (the DCA should display the correct Base Station number).

After having checked that all Base Stations are operational, proceed to the area coverage test.

4.3Area Coverage Test

The purpose of this test is to verify that the field strength is sufficient within the coverage area and that the Base Station delay values are correct. Sufficient field strength and proper Base Station delay values enable good speech quality everywhere within the covered area (rooms, elevator shafts, staircases). This test is executed with two Portable Telephones and requires two persons.

Test

1.Place the Portable Telephone in the DCA mode (refer to Section 7, "Maintenance" in this manual).

2.Call the other Portable Telephone.

3.One Portable Telephone user should now start moving around in the covered area.

4.Both users must check that a good speech quality is maintained everywhere. Pay special attention to areas such as edges of a building and areas behind metal structures where reduced speech quality is likely.

5.Mark areas where RQI is not stable on 20hex and where cracking sounds or mutes are heard.

4.4Radio Coverage Verification

This test procedure is in addition to 4.3, "Area Coverage Test."

Test

1.Place the Portable Telephone in DCA mode (refer to Section 7, "Maintenance" in this manual).

2.Call the other Portable Telephone, or any other phone, and leave the call up for the duration of the testing.

3.Select the new DCA menu item MER tests. Scroll down to GEN. Setup (yes), scroll down to DCA-SERVICE (yes), scroll down to MER tests (yes).

4.Scroll down to MER long (yes). A counter on the upper left of the screen will start counting to F03C (10 minutes). MER short counter will be set to 7D0 (20 seconds) if MER short is selected.

5.MER test Portable user should now start moving around the covered area.

6.The test can be paused and/or unpaused using thekey. The frame counter can be reset to zero restarting the test using the key. Once the test is started it will not stop unless the test is paused or the total number of frames is reached, regardless of whether or not the user stays in a MER test screen.

4-2

Comm-DCT1900/R8/mw

 

© 2000-2005

Page 336
Image 336
Nortel Networks DCT1900 manual Area Coverage Test, Radio Coverage Verification