Installation Instructions, Modular Cabinet – Installation Steps

15.Initialize the DCT1900 system. See "CSM Installer’s Quick Guide (Appendix I)

16.Place the securing bar. See Paragraph 4.12

17.Place the cabinet number labels, board name

labels and cable position labels. See Paragraph 3.8 & 3.9.

18.Commissioning. See Section 6, "Commissioning"

3.4Unpacking

The system is delivered in several cardboard boxes. To unpack, do the following:

1.Read ESD instructions in Section 1 "Safety and Regulatory Information".

2.Open the cardboard boxes and take out the shipping list.

3.Check the contents of the boxes with the shipping list .

4.Report any discrepancies or damages to cabinet(s) or board(s).

3.5Charging Portable Telephone Batteries

After installation the system must be tested with the Portable Telephones. Charge the batteries prior to installation to avoid flat batteries. Charging the batteries completely takes some time depending on the type of the charger. Refer to the DT600 Portable User Guide - LZB 119 2665, DT620 Portable User Guide - LZT 123 3105 or 9p23 User Guide - AWS1090 for battery charging instructions.

3.6Switching On/Off

Note:

Simultaneous switching on of cabinets will result in erroneous system start–up.

Multi Cabinet Configuration

zPower on: first switch on all cabinets except cabinet 1 and then switch on cabinet 1.

zPower off: first switch off cabinet 1 and then switch off the other cabinets.

Base Stations Powered via PW-EXT

Base Stations can be switched on prior to the cabinet or vice-versa.

Printer

When the RE is reset or switched on, always press the on–line button of the printer at least twice so that the printer is on–line. The RE will only detect a printer if a change from on–line to off–line state is received.

3.7Labels

With each cabinet, a label sheet is delivered containing labels of all system board names, cabinet numbers, board positions and cable positions.

3.8Board Position Label

The board position label can be placed on the leading edge of the shelf below the system boards as indicated in Figure 3–2. The label should be placed before installing the cabling.

Install-DCT1900/R8/mw

3-3

© 2000-2005

 

Page 151
Image 151
Nortel Networks DCT1900 Unpacking, Charging Portable Telephone Batteries, Switching On/Off, Labels, Board Position Label