Technical Product Manual - DCT1900

Installation Instructions, or BDVNB 101 01/3

4.5Pre–mounting of a Modular Cabinet in a One Cabinet System

1.Refer to paragrah 4.4.

2.Remove the front cover of the cabinet (see Figure 4–4):

-Remove the screws that secure the cover (1).

-Lift the front cover approximately 3/8” (2).

-Remove the cover by lifting the lower edge towards you (3).

 

2

conductive tape

 

or break-out plate

 

3

 

Front Cover

 

5

1

 

4

Drawer

1

 

6

 

Fig. 4–4 Removal of the Front Cover and the Drawer

3.Remove the drawer for easy installation:

-Open the drawer by pulling it toward you (4).

-Release the drawer by pulling the left or right hand side of the drawer down as indicated in Figure 4–4 (5) and remove the drawer (6). The drawer is hinged by the two screws on its sides. These do not need to be removed to take the drawer out. Replace the two front cover screws so that they do not get lost.

4.Remove the screw of the securing bar at the front of the Modular Cabinet and remove the securing bar. Replace the screw so it does not get lost.

5.Secure the mounting bracket to the wall, so that the bottom side of the Modular Cabinet is about 5.25 ft. above the ground using the appropriate hardware (typically #8 wood or sheet metal screws). See Fig. 4-1.

6.Hang the cabinet onto the mounting bracket and mark the location of the two retaining holes on the bottom of the cabinet.

7.Remove the cabinet and drill the lower mounting holes as needed.

8.Continue with Paragraphs 4.8 or 4.9 as needed.

4-6

Install-DCT1900/R8/mw

 

© 2000-2005

Page 160
Image 160
Nortel Networks DCT1900 manual Pre-mounting of a Modular Cabinet in a One Cabinet System