Chapter 2
Installation and Setup
2.1 Introduction
This chapter describes installation and setup procedures for the
If a problem is encountered, refer to Chapter 6 for test and diagnostic instructions.
Internal settings, adjustment, maintenance, and repairs may be performed only by a skilled technician who is aware of the hazards involved.
Always observe standard safety precautions during installation, operation, and Warning maintenance of this product.
2.2 Site Requirements and Prerequisites
The
Allow at least 90 cm (36 in) of frontal clearance for operating and maintenance accessibility. Allow at least 10 cm (4 in) clearance at the rear of the unit for signal lines and interface cables.
The ambient operating temperature of
Site Requirements and Prerequisites |