Oil in Water

Part III

 

 

 

 

 

 

 

 

 

valve(s) and wear protective goggles before opening grab sample valving as the outlet could exert pressures to 150 psig at this tap.

4utility water inlet

a This feature allows flushing of the entire sampling train including the bypass loop. It is operated manually.

Reference drawings:

aPiping Diagram, (see addendum drawings)

bOutline drawing (see addendum drawings)

5Check for shipping integrity of all components

6Inspect all connections above for proper installation recommendations

B Start up of System

On the pump control module if applicable, assure the control switch is in the off position.

1 Check that:

athe sample pump switch is off

bSample/utility valve is in the utility position.

2Apply instrument power— after assurance that all electrical interconnections are correct. Refer to section 2.3 of the manual “Testing the System”.

3Preliminarily use gravity feed into pump which is set to the inlet position, and allow all air, minor particulates, etc., to be bled through the inlet bypass before the bypass pump is turned on. Once you are assured of proper sample inlet bypass cleanliness (observe water clarity of outlet to a drain), proceed as follows:

Teledyne Analytical Instruments

Part III: 1-53

Page 143
Image 143
Teledyne 6600 manual Start up of System