2.1Unpacking the Analyzer

Oil in Water Analyzer

Part II: Analysis Unit

 

 

 

 

 

 

 

 

 

Installation

Installation of the Model 6600 Photometric Analyzer includes:

1.Unpacking

2.Mounting

3.Fluid connections

4.Electrical connections

5.Testing the system.

2.1Unpacking the Analyzer

The analyzer is shipped with all the materials you need to install and prepare the system for operation. Carefully unpack the analyzer and inspect it for damage. Immediately report any damage to the shipping agent.

2.2Installing and Connecting the Analyzer

Without Temperature Control, the system must be installed in an area where the ambient temperature is not permitted to drop below 32°F freezing nor rise above 122°F (0-50°C).

Regardless of configuration, the system must be installed on a level surface with sufficient space allocated on either side for personnel and test equipment access. Subject to the foregoing, the system should be placed as close to the sample point as possible and bolted to its supporting surface. A waterproof mastic should be liberally applied to the under surfaces of all four supporting legs of the cubicle system before placing it in position and bolting it in place.

2.2.1 User Connections

All user connections are around the periphery of the equipment panel (or cubicle) and appear in the outline diagram in the back of the manual.

Teledyne Analytical Instruments

Part II: 2-1