PREPARING FOR INSTALLATION
Installation planning checklist
To aid you in printer installation planning, the following is a checklist that lists the tasks that you and your service representative must complete before installation. If you have questions about any of these activities, contact your sales or service representative.
Use the time frames in this checklist as guidelines. It is best to consult your suppliers to determine the required lead times.
Table
|
|
|
|
|
| Date |
Week | Activity | Reference | Responsibility | completed | ||
|
|
|
|
|
|
|
Select location for the 96/4635/180 IPS. | Chapters 5 and 6 | Customer | ________ | |||
|
|
|
|
|
|
|
| Order additional documentation, if necessary. | Call XDSS at 800- | Customer | ________ | ||
|
|
|
|
|
| |
|
|
|
| Appendix B (U.S.) |
|
|
|
|
|
|
|
|
|
| Register for Xerox Customer Education classes | Appendix B | Customer and Xerox | ________ | ||
| and order tutorials, if necessary. |
|
|
| ||
|
|
|
|
|
|
|
| Schedule printer delivery. |
| Xerox | ________ | ||
|
|
|
|
|
| |
| Convert your IBM | Customer | ________ | |||
|
|
|
| sales rep. |
|
|
| Note: 180 IPS only: If you want to keep your |
|
|
| ||
| resources at 240 dpi, you may purchase a |
|
|
| ||
| special ROS board which enables the 180 IPS |
|
|
| ||
| printer to interpolate 240 dpi resources directly |
|
|
| ||
| to 600 dpi without impacting print quality. |
|
|
| ||
| Consult your sales representative about this |
|
|
| ||
| option. |
|
|
|
|
|
|
|
|
|
| ||
|
|
|
|
|
|
|
Schedule hardware delivery. | Sales rep. | Customer and Xerox | ________ | |||
|
|
|
|
|
|
|
| Prepare site: | Chapters 4 to 6 | Customer | ________ | ||
| • Provide a table with adequate space for |
|
| ________ | ||
| hardware and cables. |
|
| |||
|
|
|
| |||
| • Ensure proper electrical outlets are |
|
| ________ | ||
| installed. |
|
| ________ | ||
| • Install Token Ring to system location (if |
|
| |||
|
|
|
| |||
| appropriate). |
|
|
| ||
| • Install Ethernet to system location (if |
|
| ________ | ||
| appropriate). |
|
| ________ | ||
|
|
|
|
|
|
•Ensure proper operating environment.
•Obtain and string bus and tag cables (must be fully populated), if needed.
•Generate the host for an AFP1 device and IPL, as required
•Provide analog phone line access for optional Sixth Sense installations.
XEROX DOCUPRINT 96/4635/180 IPS INSTALLATION PLANNING GUIDE |