Section 3

Receiving & Installation

Receiving & Inspection

The Series 22H Vector Control is thoroughly tested at the factory and carefully packaged

 

for shipment. When you receive your control, there are several things you should do

 

immediately.

 

1.

Observe the condition of the shipping container and report any damage

 

 

immediately to the commercial carrier that delivered your control.

 

2.

Verify that the part number of the control you received is the same as the part

 

 

number listed on your purchase order.

 

3.

If the control is to be stored for several weeks before use, be sure that it is

 

 

stored in a location that conforms to published storage specifications. (Refer to

 

 

Section 7 of this manual).

Physical Location

The location of the 22H is important. It should be installed in an area that is protected

 

from direct sunlight, corrosives, harmful gases or liquids, dust, metallic particles, and

 

vibration. Exposure to these elements can reduce the operating life and degrade

 

performance of the control.

 

Several other factors should be carefully evaluated when selecting a location for

 

installation:

 

1.

For effective cooling and maintenance, the control should be mounted vertically

 

 

on a flat, smooth, non-flammable vertical surface. Size G+ are floor standing

 

 

NEMA 1 enclosures.

 

2.

At least two inches clearance must be provided on all sides for air flow.

 

3.

Front access must be provided to allow the control cover to be opened or

 

 

removed for service and to allow viewing of the Keypad Display. (The keypad

 

 

may optionally be remote mounted up to 100 feet from the control.)

 

 

Controls installed in a floor mounted enclosure must be positioned with

 

 

clearance to open the enclosure door. This clearance will also provide

 

 

sufficient air space for cooling.

 

4.

Altitude derating. Up to 3300 feet (1000 meters) no derating required. Above

 

 

3300 ft, derate the continuous and peak output current by 2% for each 1000 ft.

 

5.

Temperature derating. Up to 40° C no derating required. Above 40° C, derate

 

 

the continuous and peak output current by 2% per ° C. Maximum ambient is

 

 

55° C.

 

6.

50Hz Operation derating. For operation on 50Hz input power, derate the

 

 

continuous and peak output current by 15%.

 

7.

Shock Mounting. The control is designed to withstand 0.5G at 10 to 60 Hz

shock during normal operation.

Shock Mounting

If the control will be subjected to levels of shock greater than 1G or vibration greater than 0.5G at 10 to 60Hz, the control should be shock mounted. Excessive vibration within the control could cause internal connections to loosen and cause component failure or electrical shock hazard.

MN722

Receiving & Installation 3-1

Page 12
Image 12
Baldor mn722 manual Receiving & Inspection, Physical Location, Shock Mounting