Table 15: Site Preparation Checklist (continued)

Item or Task

For More Information

Performed By

Date

Verify that your rack or cabinet meets the

“Rack Requirements for EX2200

 

 

minimum requirements for the installation of

Switches” on page 39

 

 

the switch.

 

 

 

 

“Cabinet Requirements for EX2200

 

 

 

Switches” on page 40

 

 

Plan rack or cabinet location, including required

“Clearance Requirements for Airflow

 

 

space clearances.

and Hardware Maintenance for

 

 

 

EX2200 Switches” on page 42

 

 

Secure the rack or cabinet to the floor and

 

 

 

building structure.

 

 

 

Wall

 

 

 

Verify that the wall meets the minimum

“Requirements for Mounting an

 

 

requirements for the installation of the switch.

EX2200 Switch on a Desktop or Wall”

 

 

 

on page 42

 

 

Verify that there is appropriate clearance in your

“Clearance Requirements for Airflow

 

 

selected location.

and Hardware Maintenance for

 

 

 

EX2200 Switches” on page 42

 

 

Cables

 

 

 

Acquire cables and connectors:

 

 

 

Determine the number of cables needed based on your planned configuration.

Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

Plan the cable routing and management.

Related

General Safety Guidelines and Warnings for EX Series Switches on page 113

Documentation

General Site Guidelines for EX Series Switches on page 35

 

Installing and Connecting an EX2200 Switch on page 51