Power-On-Self-Test (POST)
Switch Management Port Failure (14 Blinks)
The Switch is operable. The Switch Management Port test verifies the integrity of the Ethernet data bus functionality. A failure indicates that communication over the Ethernet port will most likely be adversely affected when this failure is indicated. The Heartbeat LED will blink fourteen times between
The remainder of the Switch and all ports have passed the tests and are operable.
Hung Flash Control Code
The Switch is not operable. If the Power Good LED is lit and the Heartbeat LED and the remaining
Complete Failure
The Switch is not operable. If the Power Good LED is lit and the Heartbeat LED does not blink at all (always ON or always OFF) the Switch is not operable.
GigWorks | Diagnostics/Troubleshooting | |
Installer's/User's Manual |