SAGEM 3P@C

Figure 4-18 Completion of the installation of two combined cabinets

1.1.1.45Insulation test

Set the multimeter to the resistor range to measure the resistance between the bolt of the pressure plate assembly and the cabinet. If the circuit is disconnected, end the installation. Otherwise, it indicates the cabinet is not insulated from the supports. In this case, remove all the pressure plate assemblies to check if any insulation sleeves or pads of the supports are missing or any insulation parts are damaged. Then install the pressure plate assemblies again and repeat the insulation test.

4.1.3.Installing the Cabinet Guide Rails

Before installing the equipment, install the guide rails first inside the cabinet to bear the equipment. The installation steps are as follows:

Step 1

Determine the installation positions of guide rails.

Determine the installation positions of the guide rails according to the quantity of the chassis to be installed, and the cabling direction. Measure the installation positions and mark them.

 

 

 

Guide rails are needed to install the 10U chassis and the fan

 

 

 

module, but not needed for the air deflector frame (it only

 

prompt

 

needs hangers to get fixed).

 

 

 

 

 

 

 

Step 2

 

Install the guide rails.

 

After determining the installation positions, fasten the guide rails at such positions inside the cabinet with screws, as shown in Figure 4-19.

3P@C Installation Manual

Page 4-14

Reproduction and communication in any form prohibited without the written permission of SAGEM SA