SAGEM 3P@C

Figure 4-27 Completion of the installation of a single general chassis

Next, repeat the above operations to install multiple general chassis of 3P@C 4450E in the cabinet.

1.When installing multiple general chassis of 3P@C 4450E in the cabinet, the installation of the first one in the cabinet can start from the top installation position or the bottom one

 

 

of the cabinet.

 

 

2. If upward cabling is adopted on site, the cabling should

 

prompt

be arranged from the bottom up from the bottommost

 

 

general chassis in the cabinet. Otherwise, the cabling

 

 

should be arranged from the top down from the topmost

 

 

general chassis in the cabinet.

3P@C Installation Manual

Page 4-20

Reproduction and communication in any form prohibited without the written permission of SAGEM SA