Recommended Tools
Before you begin the installation tasks, ensure that you have the following items:
•#1 Phillips screwdriver
•#2 Phillips screwdriver
•Wrist grounding strap connected to ground
•Antistatic mat or antistatic foam
Installation Tasks
To install the rail and system into the rack, you need to perform the following tasks.
1"Installing the
2"Removing Sled Modules from the Server Enclosure" on page 228
3"Installing the Server Enclosure into the Rack" on page 228
4"Replacing Sled Modules in the Server Enclosure" on page 230
5"Installing the External PDU into the Rack" on page 231
6"Connecting the Power Cables" on page 237
7"Connecting the Server Enclosure to a Rack PDU" on page 239
8"Connecting the PDU to the Network" on page 243
9"Powering Up the Systems" on page 246