3.3.1Start-Up Procedure
SCC Start-Up
When the UPS system has been shut down, for any reason, use this procedure to
power to the critical load. This procedure gives
NOTE
The following procedure assumes that the UPS installation inspection and initial
CAUTION
The following procedure provides power to the critical load distribution system. Verify that the critical load distribution is ready to accept power. Make sure that personnel and equipment are ready for the critical load distribution system to be energized.
If your installation includes a Maintenance Bypass, you may already be supplying power to the critical load equipment through the Maintenance Bypass. If there is no power to the critical load, apply power through the UPS bypass line per the following procedure.
During a
Step 1. Before you apply power to the UPS modules, determine the position of the following circuit breakers and switches:
a.Bypass Input Breaker (BIB) - If this circuit breaker is closed, you may already have power to the critical load through the bypass line. If this breaker is closed, leave it closed. If it is open, leave it open until you are ready to energize the bypass line.
b.System Bypass Circuit Breaker (SBB) - This motorized circuit breaker (Figure 9) should be closed unless you are recovering from a Remote Emergency Power Off. You may already be supplying power to the critical load through this breaker. If this breaker is open, you will be instructed to reset it later in this procedure.
c.UPS Output Circuit Breaker - This motorized circuit breaker (see Figure 9) should be open.
d.Static Switch Disconnects - These manually operated switches (see Figure 9) will be in the ON (closed) position unless you are recovering from a shutdown. If these switches are OFF (open), you will be instructed to reset them and turn them on later in this procedure.
NOTE
Depending on SCC model, the static switch disconnects can be two circuit breakers, contactors, or
Operation 91