2.6.1Installation Checklist

-All packing materials and restraints have been removed from each cabinet.

-Each cabinet in the UPS system is placed in its installed location.

-A cabinet grounding/mounting kit is installed between any cabinets that are bolted together.

-All conduits, and cables are properly routed to the UPS and auxiliary cabinets.

-All power cables are properly sized and terminated.

-The bypass source of the supply is a four wire wye configuration. If using dual feed, the rectifier source is a three wire connection from a wye configuration.

-All telephone and network connections have been completed.

-A ground conductor is properly installed.

-Internal battery cabinet connections have been completed (plugs, etc.).

-Air conditioning equipment is installed and operating correctly.

-The area around the installed UPS system is clean and dust-free. (It is recommended that the UPS be installed on a level floor suitable for computer or electronic equipment.)

-Adequate workspace exists around the UPS and other cabinets.

-Adequate lighting is provided around all UPS equipment.

-A 120V service outlet is located within 25 feet of the UPS equipment.

-The Remote Emergency Power Off (EPO) device is mounted in its installed location and its wiring terminated inside the UPS cabinet.

-Summary alarms and/or building alarms are wired appropriately. (OPTIONAL)

-Startup and operational checks performed by authorized service personnel.

 

 

 