Getting Started
1.1Installing the UPS
The cabinet sections of the UPS are shipped on separate pallets. Use a forklift or pallet jack, rated to handle the weight of the cabinets (refer to Drawing
This is the basic sequence of the installation steps:
1.Create an installation plan for the UPS system (Chapter 1).
2.Prepare your site for the UPS system (Chapter 1).
3.Inspect, unpack, and unload the UPS cabinet sections (Chapter 1).
4.Wire the system (Chapter 2).
5.Install features, accessories, and/or options, as applicable (Chapter 3).
6.Complete the Installation Checklist (Chapter 2).
7.Have authorized service personnel perform preliminary operational checks and startup.
NOTE: Startup and operational checks should be performed only by authorized service personnel. This service is usually offered as part of the sales contract for your UPS. Contact service in advance (usually a two week notice is required) to reserve a preferred startup date.
1.1.1Creating an Installation Plan
Before beginning to install the UPS system, read and understand how this manual applies to the system being installed. Use the procedures and illustrations in the following chapters to create a logical plan for installing the system.
1.1.2Preparing Your Site
For your UPS system to operate at peak efficiency, your installation site should meet the environmental parameters outlined in this manual. If you intend to operate the system at an altitude higher than 1500 meters (5000 feet), contact your local sales or service office for important information about high altitude operation. The operating environment must meet the weight, airflow, size and clearance, requirements specified in Appendix A.