Chapter 2 Installing the Cisco 7201 Router

Connecting Power

Figure 2-24 Stripping the DC-Input Power Ground Wire

1

57019

1

0.5 inch (12.7 mm) + 0.02 inch (0.5 mm)

Step 3 If your ground wire is insulated, use a wire stripping tool to strip the 18-gauge wire, (or 16-gauge, but not smaller than the supply conductor) ground wire to 0.5 inch (12.7 mm) + 0.02 inch (0.5 mm) as shown in Figure 2-24.

Step 4 Slide the open end of the ground lug over the exposed area of the 18-gauge wire.

Step 5 Use a crimping tool to crimp each ground wire to a ground lug.

Figure 2-25 Placing the Ground Lugs, Star Washers, and Nut

PWR SLOT 2

170970

Step 6 Place the ground lugs, star washers, and nut on the grounding stud in this order:

a.Star washer

b.Ground lug

c.Star washer

d.Ground lug

e.Nut

Step 7 Tighten the nut to complete the installation.

 

Cisco 7201 Installation and Configuration Guide

2-28

OL-11364-04

Page 58
Image 58
Cisco Systems CISCO7201 manual Stripping the DC-Input Power Ground Wire