4
Power-On Procedure 4-41
Repair Information
2. Disconnect the fiber-optic cable from the SFP. Use compressed air
to blow any contaminants from the connector as shown in part A
of Figure 4-24.
Keep the air nozzle approximately 50 millimeters (two inches)
from the end of the connector and hold the can upright.
Blow compressed air on the surfaces and end of the connector
continuously for approximately five seconds
.
Figure 4-24 Clean Fiber-Optic Components
3. Gently wipe the end-face and other surfaces of the connector with
an alcohol pad as shown in part B of Figure 4-24. Ensure the pad
makes full contact with the surface to be cleaned. Wait
approximately five seconds for surfaces to dry.
4. Repeat step 2 and step 3 of this procedure (second cleaning).
5. Repeat step 2 and step 3 of this procedure again (third cleaning),
then reconnect the fiber-optic cable to the port.

Power-On Procedure

To power on the switch:
1. One alternating current (AC) power cord is required for each
power supply. Ensure power cord(s) are available to connect the
switch to facility power.

AB