3-1

Selecting a Site

The system operates reliably in a typical office environment. Choose a site that is:

Near grounded, three-pronged power outlets.

Note: For the United States and Canada, this means a NEMA 5-15R outlets for 100-120 VAC or NEMA 6-15R outlets for 200-240 VAC. For other international sites, this means three-pronged power outlets applicable for the electrical code of the region.

CAUTION: Be sure the power service connection is through a properly grounded outlet.

Each power cord can be plugged into a separate phase of a main AC supply, assuming the circuit is rated for that load.

Note: For Denmark, the system must be connected to an AC power source rated at 16 Amps.

Clean, dust-free, and well ventilated. Front and rear ventilating openings kept free of obstructions. Away from sources of heat, vibration or physical shock

Isolated from strong electromagnetic fields and electrical noise produced by electrical devices (such as air conditioners, large fans, large electric motors, radio and TV transmitters, and high-frequency security devices)

Spacious enough to provide at least five inches (13 centimeters) behind the system and three inches (eight centimeters) on each side of the system for proper cooling, airflow, and cable clearance

Easily accessible for system maintenance and installation of system upgrades.

Setup

Page 46
Image 46
Zenith Data Systems MT2000 manual Selecting a Site