Setup Options -Sections

V1.98 21/06/06

 

 

7.0SECTIONS

Figure 35: Options- Sections page

Lines

The ZYNX Sprayer can control either ‘single’ boom lines or ‘dual’ boom lines.

If ‘Single’ is selected the ‘Spray Interface’ can operate up to 6 primary boom sections.

Or 5 primary boom sections with the second line being controlled by the section valve 6 circuitry. Special plumbing and wiring considerations need to be implemented for this system.

If ‘Dual’ is selected the ‘Spray Interface’ can control 3 primary sections valves and 3 secondary sections valves, giving a total of 6 sections.

If ‘Single’ is selected and ‘Spray ECU’ is selected, then the system can operate up to:

-30 boom sections using ‘3 wire section valves’ or ‘solenoids’ with a ‘3 wire dump valve’ fitted. (Note: When using an X15 Console the number of sections is limited to 15 sections under ASC control.)

- 15 boom sections using ‘2 wire section valves’ with a ‘2 wire dump’ valve fitted.

If ‘Dual’ is selected and ‘Spray ECU’ is selected, then the system can operate up to:

-15 boom sections on the primary and 15 boom sections on the secondary line, using ‘3 wire section valves’ or ‘solenoids’ with a ‘3 wire dump valve’ fitted.

-7 boom sections on the primary line and 7 boom sections on the secondary line; using ‘2 wire section valves’ with a ‘2 wire dump’ valve fitted.

OR - 8 boom sections on the primary line and 8 boom sections on the secondary line; and no ‘Dump Valve’ fitted.

Sections

Set the number of sections by touching the calculator pad on the screen. Enter in the number of section valves on the primary line.

Setting number of sections when selecting ‘Dual’

If ‘Dual’ was selected and for example there are 8 sections on the primary line and 8 sections on the secondary line, then ‘8’ would be entered as the number of sections. See section 7.0 to set the ‘Low Speed Shutoffs’ for the primary line (section valves 1-8) and the secondary line (section valves 9-16). The ‘Low Speed Shutoff’ for the secondary line (sections 9-16) would be all set at the same speed you require the secondary line to switch ON.

Page 58

Page 58
Image 58
Topcom X20 manual Options- Sections