Upgrading CMS to the High Availability Option
CentreVu
CMS R3V8 High Availability
Connectivity, Upgrade and Administration

Setting Up CMS on an HA Server 3-40

# TCP/IP transport is only available with DEFINITY R7 and
# later switch models.
# Select the transport to the switch
# 1) X.25
# 2) TCP/IP
# Enter choice (1-2):
2
# Skip the next question if you did not enter choice 1.
# These are used for X.25 connections only.
# Select the device used for x.25 connectivity to the switch
# 1) Serial port A
# 2) Serial port B
# 3) HSI link 0
# 4) HSI link 1
# 5) HSI link 2
# 6) HSI link 3
# 7) HSI link 4
# 8) HSI link 5
# 9) HSI link 6
# 10) HSI link 7
# 11) Software loopback link 0
# 12) Software loopback link 1
# Enter choice (1-12):
# Skip the next question if you did not enter choices 11 - 12.
# These are used for testing only. If you select one of these,
# you will not be able to collect data from your ACD.
# Are you sure you want to do this? (y/n):
# Skip the next two questions if you did not enter choice 2
# (TCP/IP). These are used for TCP/IP connections only.
# If a host name is entered, the host name must be administered
#in a DNS or /etc/hosts file or the link to the switch
# will not work.
# Enter DEFINITY host name or IP Address:
192.168.2.2
# Enter DEFINITY TCP port number (5001-5999):
5001
# Maximum number of splits/skills based on switch type:
# Release(s) Value
# Definity-G3V2/Definity-G3V3/Definity-G3V4 255
# Definity-G3V5/Definity-R6/R7 600
# Definity-R8 999
# Number of splits/skills (0-Maximum):
# Maximum number of split/skill members based on switch type:
# Release(s) Value
# Definity-G3V2/Definity-G3V3/Definity-G3V4 5200
# Definity-G3V5/Definity-R6/R7/Definity-R8 10000
# Total split/skill members, summed over all
# splits/skills (0-Maximum):
1000