Upgrading CMS to the High Availability Option

CentreVu CMS R3V8 High Availability

 

 

 

Connectivity, Upgrade and Administration

 

 

Performing a New Full Maintenance Backup and Restore

3-72

 

 

 

 

 

Performing a New Full Maintenance Backup and Restore

Performing the Full Maintenance backup on the new HA server

Restoring historical data to the original server

Procedure

These procedures create a full maintenance backup on the new HA server. The backup is then used to restore CMS historical data back onto the original server.

The required full maintenance backup copies all system data to tape. For details, see “Performing a Full Maintenance Backup” on Page 3-11 .

Note:

Assuming that the new HA server is used as the HA primary server, this backup represents the first tape to be archived for the new HA system. The other backup tapes used during the provisioning process may now be reused for nightly maintenance backups.

This procedure copies historical data from the Full Maintenance backup created in the preceeding procedure.

1.Insert the Full Maintenance Backup created on the new HA server into the tape drive on the original server.

2.Log in as a CMS user.

The CMS Main Menu is displayed.

Page 92
Image 92
Lucent Technologies Release 3 Version 8 manual Performing a New Full Maintenance Backup and Restore