Procedure: Route Fiber-Optic Cables in the Shelf Assembly
Step 1 Open the fold-down front door on the cable-management tray.
Step 2 Route the cable on the card faceplate through the fiber clip on the faceplate.
GBICs do not have fiber clips; therefore, if you are routing opti cal cable from an E1000-2-G or E1000-2
card, skip to Step 3.
Step 3 Route the cables into the cable-management tray.
Step 4 Route the cables out either side of the cable-management tray through the cutouts on each side of the
shelf assembly. Use the reversible fiber guides to route cables out the desired side.
Step 5 Close the fold-down front door when all cables in the front compartment are properly routed.
Figure 1-35 shows the fold-down front door of the shelf assembly op en t o displa y th e ca ble r out ing
channel.
Tx
Rx
FAIL
ACT
SF
Fold down faceplate
Retaining clip
Slot on cable management tray
Cutout
Faceplate connector
Cable connector
39140