Section 3: Installation

Reference, Installation, and Operations Manual

June 2013

3-9000-743 Rev S

 

 

3.3.5For systems using explosion-proof conduit

1.Assemble conduit to the electronics enclosure.

If the conduit pipe is two inches or more, a conduit seal is required within 18 inches (150 mm) of the enclosure.

2.Remove the end cap nearest the conduit entry to gain access to the Field Connection Board.

3.Check to make certain that all power to the field wiring is turned OFF.

HAZARDOUS VOLTAGE INSIDE ENCLOSUREDo not open enclosure in flammable gas area. Disconnect all power to the meter.

Failure to do so may result in injury to personnel or cause damage to the equipment.

4.Pull the wires.

5.Complete connections to the Field Connection Board (see Section 3.4).

6.Select the communications driver by setting the jumpers as shown in Table 3-7through Table 3-21.

7.Replace the end cap. If desired, secure the end caps to the body with seal wires.

8.Apply the sealing compound to the conduit seal and allow to set in accordance with manufacturer specifications.

58

For systems using explosion-proof conduit