Chapter 4
Site Preparation
■Site Preparation Checklist for EX3200 and EX4200 Switches on page 81
■General Site Guidelines for EX Series Switches on page 83
■Site Electrical Wiring Guidelines for EX Series Switches on page 83
■Environmental Requirements and Specifications for EX Series Switches on page 85
Site Preparation Checklist for EX3200 and EX4200 Switches
The checklist in Table 24 on page 81 summarizes the tasks you need to perform when preparing a site for EX3200 or EX4200 switch installation.
Table 24: Site Preparation Checklist
Item or Task
Environment
Verify that environmental factors such as temperature and humidity do not exceed switch tolerances.
For More Information | Performed By | Date |
“Environmental Requirements and Specifications for EX Series Switches” on page 85
Power
Measure distance between external power sources and switch installation site.
Locate sites for connection of system grounding.
Calculate the power consumption and | “Power Specifications for EX3200 |
requirements. | and EX4200 Switches” on page 97 |
Hardware Configuration |
|
Choose the number and types of switches you | “EX3200 and EX4200 Switches |
want to install. | Hardware Overview” on page 3 |
Rack or Cabinet |
|