Installing the UPS System
Installation Checklist
-All packing materials and restraints have been removed from each cabinet.
-Each cabinet in the UPS system is placed in its installed location.
-The front shipping bracket is installed and adjusted, if the cabinet is not installed permanently.
-A cabinet grounding/mounting kit is installed between any cabinets that are bolted together.
-All conduits and cables are properly routed to the UPS and any ancillary cabinets.
-All power cables are properly sized and terminated.
-Neutral conductors are installed or bonded to ground as per requirements.
-Battery cables are terminated on E4 (+) and E5
-Battery UV trip and Aux contact signal wiring is connected from the UPS to the battery breaker.
-LAN and telephone drops are installed.
-All telephone and LAN connections have been completed.
-A ground conductor is properly installed.
-Air conditioning equipment is installed and operating correctly.
-The area around the installed UPS system is clean and
-Adequate workspace exists around the UPS and other cabinets.
-Adequate lighting is provided around all UPS equipment.
-A 120 Vac service outlet is located within 7.5 meters (25 feet) of the UPS equipment.
-The REPO device is mounted in its installed location and its wiring is terminated inside the UPS cabinet. The REPO switch must be a
-The
-Alarm relays and building alarms are wired appropriately. (OPTIONAL)
-A remote battery disconnect control is mounted in its installed location and its wiring is terminated inside the UPS and battery cabinet. (OPTIONAL)
-Accessories are mounted in installed locations and wiring is terminated inside the UPS cabinet. (OPTIONAL)
-The debris shield covering the UPS cabinet ventilation grill is removed.
-Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.