Chapter 2
UPS Installation Plan and Unpacking
Use the following basic sequence of steps to install the UPS:
1.Create an installation plan for the UPS system (Chapter 2).
2.Prepare your site for the UPS system (Chapter 2).
3.Inspect and unpack the UPS cabinet (Chapter 2).
4.Unload and install the UPS cabinet, and wire the system (Chapter 3).
5.Install features, accessories, or options, as applicable (Chapters 5 and 6).
6.Complete the Installation Checklist (Chapter 3).
7.Have authorized service personnel perform preliminary operational checks and startup.
NOTE Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or the warranty terms specified on page
2.1 Creating an Installation Plan
Before installing the UPS system, read and understand how this manual applies to the system being installed. Use the procedures and illustrations in the following chapters to create a logical plan for installing the system.
2.2 Preparing the Site
For the UPS system to operate at peak efficiency, the installation site should meet the environmental parameters outlined in this manual. If the UPS is to be operated at an altitude higher than 1500m (5000 ft), contact your Eaton service representative for important information about high altitude operation. The operating environment must meet the weight, clearance, and environmental requirements specified in Drawing
The UPS cabinets use forced air cooling to regulate internal component temperature. Air inlets are in the front of the cabinet and outlets are in the top. You must allow clearance in front of and above each cabinet for proper air circulation.