Procedure 5. A2, A3, A4, and AS Assemblies
Procedure 5. A2, A3, A4, and A5 AssembliesRemoval
1.Remove the analyzer’s cover.
2.Place the analyzer on its right side frame.
3.Remove the eight screws holding the A2, A3, A4, and A5 assemblies to the top of the analyzer. These screws are labeled (a), (3), and (4) in Figure
4.Remove ribbon cable W4 from A2J6. See Figure
Caution | Do not fold the board assemblies out of the analyzer one at a time. Always |
| fold the A2 and A3 assemblies as a unit and the A4 and A5 assemblies as |
| a unit. Folding out one assembly at a time binds the hinges attaching the |
| assemblies and may damage an assembly and hinge. |
|
|
5.The board assemblies are attached to the analyzer’s right side frame with two hinges. Fold both the A2 and A3 assemblies out of the analyzer as a unit.
6.Fold both the A4 and A5 assemblies out of the analyzer as a unit.
7.Remove the cables from the assembly being removed, as illustrated in Figure
8.Remove the two screws that attach the assembly being removed to its two mounting hinges.
Caution | Do not torque shield pozidrive screws to more than 5 |
| excessive torque will cause the screws to stretch. |
|
|
Assembly Replacement