Repair Information
b.The amber system error (ERR) LED on the switch front panel blinks momentarily while the switch is tested.
c.The green LEDs associated with the Ethernet port blink momentarily while the port is tested.
d.The green and amber LEDs associated with the ports blink momentarily while the ports are tested.
4.After successful POST completion, the green power (PWR) LED remains illuminated and all other LEDs extinguish.
5.If a POST error or other malfunction occurs, go to "MAP 0000: Start MAP" on page
NOTE: When powering on the switch after removing and replacing a faulty FRU, the amber system error LED may remain illuminated. Clear the system error LED as part of the replacement procedure.
Power-Off Procedure
To
1.Notify the customer the switch is to be powered off. Ensure the customer’s system administrator quiesces Fibre Channel frame traffic through the switch and sets attached devices offline.
2.Set the switch offline ("Set Offline State" on page
3.Turn off both power switches at the rear of the unit.
4.If servicing the switch, disconnect the power cord(s) from the input power module at the rear of the switch. This step is not required when performing a power cycle.
Reset or IPL the Switch
A switch reset using the IML button (at the switch front panel) or IPL (at the product manager application) are functionally equivalent. They:
•Perform partial