Lucent Technologies 555-661-140 manual Installing the Power Supply

Models: 555-661-140

1 355
Download 355 pages 10 Kb
Page 85
Image 85

MERLIN LEGEND Communications System Release 6.1

Issue 1

Installation 555-661-140

August 1998

Installing the Control Unit

Page 2-20

Installing the Power Supply

 

 

Installing the Power Supply

! WARNING:!

Do not attach any cables or power cords to the power supply until it is installed in the carrier.

Do not power up the control unit until all of the modules and power equipment are installed. Once they are installed, refer to “Powering Up the System,” later in this chapter. Failure to comply with this procedure can result in shock hazard and/or damage to the equipment.

If you are upgrading an older system and a ring generator is specified in the system forms (Control Unit Diagram), install it in the power supply before putting the power supply in the carrier. The procedure is detailed in Maintenance and Troubleshooting.

For expansion carriers with older power supply modules only, a copper shield must be installed on the power supply before installing it in the carrier. The procedure is explained in “Installing a Copper Shield,” later in this chapter.

Before touching leads, connectors, pins, and other components, use a properly grounded wrist strap, to prevent damage from electrostatic discharge (ESD).

Remove the protective cover from the gold-finger connector (on the back of the power supply) before inserting it into the carrier.

Installing the power supply can involve as many as four procedures, depending on the system configuration. The procedures are:

Turning off all power to the control unit

Installing a copper shield [for older power supply modules (391A1, 391A2, 391B1) only]

Installing the ferrite cores

Page 85
Image 85
Lucent Technologies 555-661-140 manual Installing the Power Supply