Chapter 3 System Preparation
204 September 2002 HPSS Installation Guide
Release 4.5, Revision 2
Disaster recovery requirements
Disaster recovery test plan
Pre-Production Test Plan, including:
Customer's requirements (users, admin, management, and operations staff) for the
production storage system considering all involved hardware and software, which
mayinclude detailed requirements in one or more of the following areas depending on
customer requirements:
Functionality
Single-transfer performance
Aggregate performance
Maximum number of concurrent requests
System reliability given a specific loading profile over a specific period of time
Interoperability with other software
Test procedures to verify that, when successfully executed, will prove that the above
expectations will be satisfied once the entire mass storage system (software and
hardware) is put into production.
Hardware and prerequisite software support arrangements, including vendor and
customer id numbers and procedures for obtaining hardware, AIX, DCE, Encina, and
Sammi support.
Thematerial can be placed on the web for easy accessibility by all review participants. The material
should be made available to all reviewers at least 2 days prior to the review.