Appendix G High Availability
HPSS Installation Guide September 2002 571
Release 4.5, Revision 2
Figure H-18 Starting Cluster Services
2. Alternatively,itis possible to use a slightly different SMIT path to start the Cluster Manager
onthe local node. Of course, this requires logging into each node independently to activate
both Cluster Managers.
% smitty hacmp
Cluster Services
-> Start Cluster Services
Take the defaults and press <Enter>.
G.10.2 Shutdown the Cluster
The procedure for shutting the cluster down is almost exactly the same as starting the cluster.
The SMIT path that will let you shut down both nodes at once is:
% smitty hacmp
Cluster System Management
-> HACMP Cluster Services
-> Stop Cluster Services
This SMIT path that requires shutting down both nodes independently is: