13-5
User Guide for Resource Manager Essentials 4.1
OL-11714-01
Chapter 13 Tracking Network Changes Using Change Audit
Performing Maintenance Tasks
Step 1 Select Resource Manager Essentials > Admin > ChangeAudit > Force Purge.
The Purge Policy dialog box appears.
Step 2 Enter the information required to perform a Forced Purge:
Field Description
Purge change audit
records older than
Enter the number of days. Only Change Audit records older than the number of days that you specify
here, will be purged.
Purge audit trail
records older than
Enter the number of days. Only Audit Trail records older than the number of days that you specify
here, will be purged.
See Tracking RME Server Changes Using Audit Trail for further information.
Scheduling
Run Type You can specify when you want to run the force purged job for Change Audit and Audit Trail records.
To do this, select one of these options from the drop down menu:
• Immediate—Runs this task immediately.
• Once—Runs this task once at the specified date and time.
Date Enter the start date in the dd-mmm-yyyy format, for example, 02-Dec-2003, or click on the Calendar
icon and select the date.
The Date field is enabled only if you have selected Once as the Run Type.
at Enter the start time, in the hh:mm:ss format (23:00:00).
The At field is enabled only if you have selected Once as the Run Type