Measurement Performance

During meter verification, you can choose between setting digital communications process variable values to the configured fault indicator or the last measured value. The values will remain fixed for the duration of the test (approximately four minutes). Disable all control loops for the duration of the procedure, and ensure that any data reported during this period is handled appropriately.

To perform meter verification:

Using ProLink II, follow the procedure illustrated in Figure 10-1.

Using the display menu, follow the procedure illustrated in Figure 10-2.For a complete illustration of the meter verification display menu, see Figure B-8.

Using a DeviceNet tool, follow the procedure illustrated in Figure 10-3.

For a discussion of meter verification results, see Section 10.3.1.

Figure 10-1Meter verification procedure – ProLink II

Tools >

Meter Verification >

Structural Integrity Method

Verify configuration

parameters

View previous test data

Yes

 

Next

 

 

 

 

 

 

Back(1)

Graph of results

 

Enter optional test data

 

 

 

 

 

 

Next

 

Next

 

 

View report (option to print

 

 

 

 

 

 

 

 

or save)

 

Initialize and start meter

 

 

 

verification

 

 

Finish(2)

 

 

 

 

 

Start

 

 

 

Fault

Hold last

 

 

configuration

value

 

 

 

Progress bar shows

Abort

 

 

test in progress

 

 

 

 

Abort

Fail

Pass

Back

 

 

 

 

Next

 

Rerun

 

 

 

 

(1) If the graph was viewed at the beginning of the procedure,

 

No

 

 

 

clicking Back here will return to the beginning of the procedure

test?

 

 

 

 

 

 

 

 

 

 

 

 

(along the dotted line).

 

 

 

 

 

(2)The results of the meter verification test are not saved until Finish is clicked.

92

Micro Motion® Model 2400S Transmitters for DeviceNet

Page 100
Image 100
Emerson Process Management 2400S manual 1Meter verification procedure ProLink