Step 4. Remove the rack bracket from across the width of the 19" rack by unscrewing the two 10-32 x 5/8" screws.

Step 5. Slide the unit out of the rack.

Replacing the SNC 5100

Step 1. Remove the SNC 5100 from the protective bag.

Install the new SNC 5100 in the rack.

Step 2. Plug the power cable in.

Step 3. Complete the "Final Diagnostic Tests".

Final Diagnostic Tests

After the unit has been replaced, a complete diagnostic check must be performed to ensure that no new problems have been introduced.

For further information about the procedures and commands used in this section, see “Connecting to the Service Port” on page 95 and “Diagnostic Command Reference” on page 187.

Final Test Preparation

Step 1. Connect a service terminal to the SNC 5100.

For information about how to do this, see “Connecting to the

Service Port” on page 95.

Step 2. Reattach the power cord to the SNC 5100.

Step 3. Turn on the SNC 5100 and wait until it finishes booting.

Step 4. Press the Enter key on the service terminal.

If the prompt is not displayed, go to “Service Port MAP” on page 75.

Step 5. From the Service Terminal, enter the diagBoot command.

Step 6. Wait until the SNC 5100 has finished booting into diagnostic mode.