2.Issue a request for creating a TCz Synchronous pair to the primary subsystem MCU where TCz Synchronous is installed.

3.Wait until the status of the TCz Synchronous pair becomes Duplex.

4.Issue a request for creating a URz pair to the MCU where URz is installed.

5.When creating a URz pair, be sure to select a value from 1 to 3 as the mirror ID.

6.Wait until the status of the URz pair becomes Duplex.

Note: You must ensure that the TCz Synchronous pair status changes to Duplex before the URz pair status changes to Duplex. If you have made a request for changing the URz pair status to Duplex before the TCz Synchronous pair status changes to Duplex, the request will be rejected.

For detailed information about installing and using TCz Synchronous, please refer to TrueCopy for IBM z/OS User's Guide. For detailed information about URz journal group configuration, see section Journal Group Operations. For detailed information about port configuration, see section Configuring Port Attributes.

Transferring Business Tasks Back to the Primary Site

After performing disaster recovery as explained in section Disaster Recovery in a 3DC Cascading Configuration and removing failures at the primary site or other locations, you will be able to transfer business tasks back to the primary site.

To transfer business tasks back to the primary site, follow the procedure below. Business Continuity Manager is used in this procedure:

7.Stop business tasks at the secondary site.

8.If the disaster recovery operation (as explained in section Disaster Recovery in a 3DC Cascading Configuration) could not change the URz pair status to Duplex and could not reverse the copy direction, please use Business Continuity Manager to execute the YKRESYNC REVERSE command onto the journal groups that will make a URz pair between the intermediate site and the secondary site.

Note: YKRESYNC is a command for re-establishing a pair.

1.Wait until the status of the URz pair changes to Duplex.

2.Use Business Continuity Manager to execute the YKSUSPND REVERSE command onto the journal groups that will make a URz pair between the intermediate site and the secondary site.

Note: YKSUSPND is a command for splitting a pair and stopping the copy operation temporarily.

1. Wait until the status of the URz pair changes to Suspend.

3-38

Chapter 3 Preparing for Universal Replicator z/OS Operations

Hitachi Universal Replicator for IBM /OS User’s Guide

Page 104
Image 104
Hitachi MP-96RD625-01 manual Transferring Business Tasks Back to the Primary Site