Commissioning (software)

4.3Configuring the system in online mode

3.Select either a servo or a vector drive object.

4.Click "Close" to complete automatic configuration.

The configuration data is uploaded (Upload to PG) automatically as soon as automatic commissioning is completed.

Note

If the firmware of the SINAMICS components differs from the firmware on the CF card, the firmware of the SINAMICS components will be upgraded automatically.

5.Click "Close" to exit automatic configuration.

Figure 4-14 Automatic configuration completed

6.Perform the "Copy RAM to ROM ..." function on the D410 and on SINAMICS Integrated. This saves the project on the CF card and does not need to be reloaded after a switch- on/switch-off.

Note

After having updated the firmware of a SINAMICS component, go offline and then switch off the power supply of the upgraded component (Power Off/On).

Result

The DRIVE-CLiQ components transferred to the user project by means of the automatic configuration are displayed in the Project Navigator.