StorageTek 6 manual •Prior to reestablishing the link

Models: 6

1 718
Download 718 pages 10.93 Kb
Page 658
Image 658
•Prior to reestablishing the link:

The original primary control data set continues to operate for ACS0 only. As the library operates, any updates occurring to either control data set after the link was severed causes the data sets to be unsynchronized. It is a difficult task to resynchronize the data for both data sets.

Possible solutions to resynchronize the data sets include:

Execute the AUDIt utility and reconcile the differences between the primary control data set and the secondary data set. This solution is not recommended because of the time required to perform a full audit operation.

Execute the BACKup utility, specifying OPTion(Analyze), immediately followed by the RESTore utility, specifying GENerate(YES). The BACKup utility performs error and comparison checking of records for the data sets and enables you to reconcile the differences. With this utility, you can ensure that the two data sets are properly synchronized. Library operation can be resumed at a high confidence level.

Prior to reestablishing the link:

1.Bring the HSC down.

2.Reestablish the link.

3.Run BACKup OPTion(Analyze) and RESTore GENerate(YES).

4.Bring the HSC up.

5.Use the discrepancy report produced by the backup to determine discrepancies between copies of the CDS.

Refer to Chapter 4, “Utility Functions” on page 169 and the AUDIt, BACKup, and RESTore utilities for detailed information.

628VM/HSC 6.0 System Programmer’s Guide

1st ed., 6/30/04 - 312579601

Page 658
Image 658
StorageTek 6 manual •Prior to reestablishing the link