Scheduling file policies

You can schedule a time when FMA runs all file policies for a specific volume.

Note If the server is offline when a policy is scheduled to start, the policy does not run again until the next scheduled time after the server is started.

To schedule file policies

1.In the left pane of the FMA user interface, select Managed Volumes.

2.In the right pane, double-click the volume on which you want to schedule file policies.

3.In the Scheduling area, click Change.

4.In the Schedule Options dialog box, change the following information as necessary:

Start times—The time (in 24-hour notation) when FMA starts migrating files based on policies. If no start time is set, file policies are not processed for this volume unless they are run manually.

Day of month—The days of the month when FMA runs policies.

Months—The months when FMA runs policies.

Days of week—The days of the week when FMA runs policies.

5.To limit the duration of the policy run, select Max duration (minutes) and set the number of minutes that FMA spends running policies.

6.Click OK.

To run policies manually

1.In the left pane of the FMA user interface, select Managed Volumes.

2.In the right pane, double-click the volume on which you want to run policies.

3.In the Scheduling area, click Start now.