FRU

Action

 

 

 

5

LVPS

CAUTION: When taking measurements for AC power, observe all

 

LVPS to fuser AC cable

safety precautions.

 

Check the AC line voltage between the pins on the fuser end of the

 

 

 

 

LPVS to fuser AC cable. If the voltage is correct, unplug the AC

 

 

power cord from the LVPS cable. If the voltage is correct, unplug the

 

 

AC power cord from the LVPS, pull the LVPS out far enough to be

 

 

able to check the voltage between CN-1 and CN1-3 on the LVPS

 

 

board. Plug in the power cord, turn the printer on and check the

 

 

voltage. If correct, replace the LVPS to fuser AC cable; if incorrect,

 

 

replace the LVPS assembly.

 

 

Note: If the fuses in the LVPS are blown, the LVPS assembly must be

 

 

replaced.

 

 

 

6

Fuser top cover assembly

Check to make sure that the thermistor is installed correctly to J5 on

 

(thermistor, thermistor

the fuser control card. If installed correctly check the cable for any

 

cable)

signs of damage. If any problems are found, replace the fuser top

 

Fuser to system board DC

cover assembly. If no problem is found, check the fuser to system

 

board DC cable for correct installation at J1 on the fuser control card.

 

cable

 

If no problem is found, check the fuser to system board cable for

 

 

 

 

correct installation at J10 on the system board.

7Error code 920.06 Carefully check the installation of the LVPS to system board cable to

 

displayed

J27 on the system board and to CN2 on the LVPS. If the cable is not

 

LVPS

seated or installed properly, reseat the cable and retry the printer. If

 

the cable is installed correctly, replace the following FRUs in the order

 

System board

 

shown:

 

System board to LVPS

LVPS assembly. See “Low voltage power supply removal” on

 

cable

 

page 4-54.

 

 

System board assembly. See “System board and inner shield

 

 

 

removal” on page 4-76.

 

 

LVPS to system board cable.

 

 

 

8

Fuser assembly

If no problem is found up to this point, then replace the following in

 

 

the order shown:

 

 

Fuser assembly. See “Fuser assembly removal” on page 4-26.

 

 

System board assembly. See “System board and inner shield

 

 

 

removal” on page 4-76.

 

 

LVPS. See “Low voltage power supply removal” on

 

 

 

page 4-54.

2-88Service Manual

Page 124
Image 124