Adding, Removing, or Replacing a DC-Input Power Supply
Verifying the Installation of a DC-Input Power Supply
To verify the operation of a
To verify the operation of a
Step 1 First, verify that the following conditions are satisfied:
•The power supply is completely inserted into the bay and secured in place with the captive installation screw.
•A vacant power supply bay is covered with a blank filler panel.
•The source DC power cables are connected properly to the terminals on the power supply faceplate.
•The source end of the DC power cable is properly connected to the main source DC circuit breaker.
•The main source DC circuit breaker servicing the
•The source DC voltage is within the range indicated on the power supply faceplate.
•If two
Step 2 Assuming that you have not already done so, set the rotary power switch of the newly installed power supply to the ON position.
Step 3 Observe the behavior of the green INPUT OK LED on the power supply faceplate for the following conditions:
•If the source DC voltage is within the proper range, the INPUT OK LED goes on.
•If the green INPUT OK LED does not go on, determine if
(a)The main source DC circuit breaker is on.
(b)The source DC power cables are connected properly to the terminals on the power supply faceplate.