Cut-to-Service

10

 

Do not perform any tasks in this chapter until you complete the necessary cut-to- service tasks in the Cut-to-Servicechapter of INTUITY System Software Installation, 585-310-140. The installation document explains when you must use the instructions in this chapter. If you have not performed the tasks in the installation document, complete the tasks now.

This chapter explains how to administer the switch for the INTUITY system cut-to- service process. Cutting over an INTUITY system requires you to change the coverage path used by all subscribers. All INTUITY system initial administration, switch administration, and acceptance tests must be completed before you cut the system into service. To perform the cut-to-service process, you must perform the following

Cutting to service on the NEAX 2400 MCI switch is a phone-based task. A procedure must be performed at each subscriber telephone to administer the extension on the switch. Although each telephone only requires administration once, the process may require a large amount of time if you have a large subscriber base.

Instead of having the system administrator perform the subscriber telephone tasks, have each subscriber perform the task. Use an In-serviceletter to provide instructions to the user for performing the tasks. Use the instructions in this chapter to write the user instructions. Determine the best cut-to-service strategy in advance and plan a time to administer the subscriber extensions.

NOTE:

When you cut the subscribers into service, all subscribers receive INTUITY System service. You need to prepare the subscribers and train the system attendants before you cut to service.

Issue 2 December 1995 10-1

Page 109
Image 109
AT&T 2400 manual Cut-to-Service