Epson Research and Development Page 9
Vancouver Design Center
S5U13705B00C Rev. 2.0 Evaluation Board User Manual S1D13705
Issue Date: 2002/09/16 X27A-G-014-02
3 Installation and Configuration
The S5U13705B00C is designed to support as many platforms as possible. The
S5U13705B00C incorporates a DIP switch and seven jumpers which allow both evaluation
board and S1D13705 LCD controller to be configured for a specified evaluation platform.

3.1 Configuration DIP Switches

The S1D13705 has configuration inputs (CNF[3:0]) and BS# input, which are read on the
rising edge of RESET#. In order to configure the S1D13705 for multiple Host Bus Inter-
faces a six-position DIP switch (SW1) is required. The following figure shows the locat ion
of DIP switch SW1 on the S5U13705B00C.
Figure 3-1: Configuration DIP Switch (SW1) Location
DIP Switch - SW1