INSTALLATION
Off-Premises Stations (TN742, TN746B in R3V2)
An
Note: Only the local telephone company can install the interconnections for the OPS.
The connections between the network interface and the 700A Jacks are described under “Connect Network Interfaces to TAE Jacks.” (Only the TN742 CP supports this feature.)
1.Trace the OPS pairs through the network interface to their termination on the TAE.
2.Install secondary wiring protectors. (See Table
3.Cut down one end of a cable pair on the 700A and the other to a 858A Adapter on the SIP.
4.Connect an octopus cable to a TN742 circuit pack.
5.Connect the octopus cable legs to the adapter wired in Step 3 above.
6.Document all connections.
Out-of-Building Voice Terminals (TN742, TN746B in R3V2)
A
1.At the remote location, connect the
2.Using
3.Run the cable from the remote protection device to the System 25 equipment location.