X20 Sprayer Reference Manual
•15 Boom Sections using 2 wire section valves with a 2 wire dump valve fitted.
If Dual is selected the Spray Interface can control 3 primary sections valves and 3 secondary sections valves, giving a total of 6 sections.
If Dual is selected and Spray ECU (see page
•15 Boom Sections on the primary and 15 Boom Sections on the secondary line, using 3 wire section valves or solenoids with a 3 wire dump valve fitted
•7 Boom Sections on the primary line and 7 Boom Sections on the secondary line using 2 wire section valves with a 2 wire dump valve fitted
•8 Boom Sections on the primary line and 8 Boom Sections on the secondary line and no Dump Valve fitted.
Sections
Set the number of sections by pressing the calculator icon. See Appendix A for help with using the calculator icon.
Enter the number of section valves on the primary line.
Setting the Number of Sections When Selecting Dual
If Dual was selected and, for example there are 8 sections on the primary line and 8 sections on the secondary line, then ‘8’ would be entered as the number of sections.
See page