Rack Mount Cabinets

Inspection

Inspection

When the system is received, examine all packages carefully and note any visible damage. If any damage is found, do not open the packages. Contact the delivery carrier immediately and make the proper claims.

After unpacking (and before installing), check the system against the packing list and inspect all equipment for damage. If equipment is missing or damaged, contact your supplier immediately.

Be sure to retain original packaging materials for re-use when storing or transporting system hardware.

Site Requirements

Space

Do not install other devices between cabinets.

No gap should exist between the cabinets. This provides EMC by connecting 2 screws between cabinets.

The 3.28 ft. (1m) of space is necessary for the front and back of the rack to make installation and repair easy. Installation and wiring are done from the front and rear of the cabinets.

A space measuring 1.75 inches (44.5mm) must always be left above the top of the rack mounted cabinet for the purpose of ventilation. It is also necessary to have a space between the top/bottom cabinet and any other device (shown below).

1.75inches

(44.5mm)

10.5inches

(267 mm)

Front View

Other Device

CRSUB672A

CRSUE672A

CRSUE672A

Other Device

 

Side View

3.28'

3.28'

 

Wall

Figure 5-1 Required Space

Ventilation

50% or more of the front and back of the cabinet must be left open for ventilation.

Cabinet rack must always be left open for ventilation.

5-2

Strata CTX I&M 06/04

Page 190
Image 190
Toshiba CTX28 manual Space, Ventilation